Tyre Van Conversion – Installation Procedure
Purpose:
This procedure sets out the standard Vehicle Installers process for completing a tyre van conversion from vehicle arrival through to final testing.
Before beginning work, the installer must check the individual vehicle project in MY Workshop. The project specification takes priority where a particular vehicle has different requirements.
Installer: ____________________
Vehicle Registration: ____________________
Vehicle: ____________________
Project / Job Number: ____________________
Start Date: ____________________
Target Completion: ____________________
Stage 1 – Vehicle Arrival & Job Preparation
Before any work begins, open the vehicle’s project in MY Workshop and check the complete job specification.
Check the project
☐ Correct vehicle has arrived
☐ Vehicle registration matches project
☐ Conversion specification checked
☐ Equipment list checked
☐ Optional extras checked
☐ Any special customer instructions identified
☐ Existing equipment to remain identified
☐ All required parts present
Check Vehicle Installers stock
Before starting the conversion, check there is sufficient workshop stock to complete the installation.
This includes:
☐ Electrical cable
☐ Battery cable
☐ Terminals and cable lugs
☐ Ferrules
☐ Heat shrink
☐ Cable protection/conduit
☐ Cable ties and fixings
☐ Fuses
☐ Circuit breakers
☐ Nuts, bolts and washers
☐ Rivnuts/fixings
☐ Electrical connectors
☐ Air fittings
☐ Other required consumables
Do not wait until halfway through the conversion to identify missing stock.
Take photographs of:
☐ Front of vehicle
☐ Rear
☐ Both sides
☐ Cab
☐ Load area
☐ Existing damage
☐ Existing equipment
Upload required photographs to MY Workshop.
Estimated Stage Time: To be added
Stage 2 – Strip Out & Equipment Inspection
Remove:
☐ Existing shelving
☐ Existing racking
☐ Unwanted boarding
☐ Unwanted flooring
☐ Previous equipment/installations where instructed
IMPORTANT: Check MY Workshop before removing existing boarding or flooring. Some projects may specify that existing boarding/flooring is to remain.
Unbox all new equipment
Do this at the beginning of the project, not when each component is eventually required.
Remove packaging and inspect every major component.
Check for:
☐ Transit damage
☐ Missing components
☐ Missing brackets
☐ Missing cables
☐ Missing connectors
☐ Incorrect equipment
☐ Incorrect voltage/specification
Any problem should be reported immediately.
The sooner damaged or missing equipment is identified, the sooner replacement parts can be arranged without delaying the build.
Estimated Stage Time: To be added
Stage 3 – Component Positioning & Installation
Depending on specification, this may include:
☐ Internal lighting
☐ External work lights
☐ Warning beacons
☐ Battery chargers / DC-DC chargers
☐ Circuit breakers
☐ Fuse/distribution equipment
☐ Control panel
☐ Battery monitoring equipment
☐ Step-down converters
☐ Isolation switches
☐ Cameras/security equipment
☐ Other electrical accessories
Check the proposed position before drilling or permanently fixing equipment.
Consider:
Cable routing • access for servicing • protection from damage • heat • ventilation • equipment clearance • future maintenance
Once the components are correctly positioned, the wiring stage can begin.
TRAINING VIDEO: Component positioning and mounting
[VIDEO TO BE ADDED]
Estimated Stage Time: To be added
Stage 4 – 12V Electrical Installation
This stage may include:
☐ Lighting circuits
☐ Beacon circuits
☐ Control panel wiring
☐ 12V accessory circuits
☐ Earth connections
☐ Fuse protection
☐ Circuit breakers
☐ 24V-to-12V step-down equipment where required
☐ Cable protection
☐ Cable wrapping/looming
Vehicle Installers Wiring Standards
Cable sizes:
[TABLE TO BE ADDED]
Fuse/circuit breaker sizes:
[TABLE TO BE ADDED]
Approved earth points:
[GUIDANCE TO BE ADDED]
Approved connectors:
[GUIDANCE TO BE ADDED]
Training Videos
Joining Electrical Cable
[VIDEO]
Choosing & Using Different Connectors
[VIDEO]
Wrapping and Protecting Wiring Looms
[VIDEO]
Creating Correct Earth Connections
[VIDEO]
Wiring the Vehicle Installers Control Panel
[VIDEO]
Correct Use of Circuit Breakers
[VIDEO]
24V-to-12V Step-Down Installation
[VIDEO]
Estimated Stage Time: To be added
Stage 5 – 230V Electrical Installation
Complete the 230V installation according to the vehicle specification.
This may include:
☐ Consumer unit
☐ Circuit protection
☐ Socket outlets
☐ Equipment supplies
☐ Inverter supply/output
☐ Cable routing and protection
☐ Terminations
Training Videos
Consumer Unit / Circuit Protection
[VIDEO]
230V Socket Installation
[VIDEO]
Using Ferrules & Correct Cable Termination
[VIDEO]
230V Wiring Specification
Cable specification:
[TO BE ADDED]
Circuit protection:
[TO BE ADDED]
Testing requirements:
[TO BE ADDED]
Estimated Stage Time: To be added
Important: 230V work must only be undertaken by personnel who are competent and authorised by Vehicle Installers for the work being performed. Follow the approved electrical design and testing procedure for the installation.
Stage 6 – Connecting the 12V / 24V / 230V Power System
The separate electrical systems can now be connected according to the project specification.
Typical components include:
Vehicle electrical system → DC-DC charger → auxiliary battery/battery bank → isolation/cut-off → circuit protection → inverter → 230V distribution
Complete and check:
☐ DC-DC charger connections
☐ Auxiliary battery connections
☐ Main fuse/circuit protection
☐ Battery isolation switch
☐ Inverter supply
☐ Earth/negative connections
☐ 12V distribution
☐ 24V distribution where applicable
☐ 230V inverter connection
Cable Size & Protection
| Circuit | Cable Size | Fuse/Breaker | Notes |
|---|---|---|---|
| Starter → DC-DC | TBC | TBC | |
| DC-DC → Battery | TBC | TBC | |
| Battery → Inverter | TBC | TBC | |
| 12V Distribution | TBC | TBC | |
| 24V Distribution | TBC | TBC |
We’ll populate this as you work through the next build, rather than guessing one universal size now. Cable size and protection need to match the actual circuit/load and installation.
Estimated Stage Time: To be added
Stage 7 – Boarding & Flooring
Fit:
☐ Flooring
☐ Side boarding
☐ Door boarding
☐ Protective panels
☐ Equipment mounting panels where required
Check MY Workshop for the required finish.
Ensure previously installed cables and equipment are not damaged or trapped during boarding.
TRAINING VIDEO: Boarding around installed electrical systems
[VIDEO TO BE ADDED]
Estimated Stage Time: To be added
Stage 8 – Inverter, Air System & Tyre Equipment
Complete the final major equipment installation. Check Added attachments fore layout.
Inverter System
☐ Mount inverter securely
☐ Check ventilation/clearance
☐ Install correct cable terminations
☐ Connect isolation/protection
☐ Complete final connections
TRAINING VIDEO: Correct inverter cable ends and connections
[VIDEO]
Air System
Install as specified:
☐ Compressor
☐ Air receiver where applicable
☐ Hose reel
☐ Air lines
☐ Regulators
☐ Couplings
☐ Drain/access points
TRAINING VIDEO: Correct airline fittings and connections
[VIDEO]
Tyre Equipment
Position and securely install:
☐ Tyre changer
☐ Wheel balancer
☐ Compressor
☐ Associated equipment
Check working clearance and accessibility before final tightening.
Estimated Stage Time: To be added
Stage 9 – Testing & Commissioning
The complete installation must be tested.
12V / 24V
☐ Internal lights
☐ External work lights
☐ Warning beacons
☐ Control panel
☐ Accessories
☐ DC-DC charger operation
☐ Charging voltage
☐ Battery monitoring
☐ Step-down converter operation
☐ Isolation switch
230V
☐ Inverter operation
☐ Socket outlets
☐ Consumer unit/protection
☐ Equipment supplies
☐ Required electrical tests completed
Air System
☐ Compressor operates correctly
☐ Compressor reaches operating pressure
☐ Automatic cut-off operates
☐ Air lines checked
☐ Connections checked for leaks
☐ Hose reel tested
Tyre Equipment
☐ Tyre changer operational
☐ Wheel balancer operational
☐ Equipment securely mounted
☐ Working clearances checked
Full Load Test
The complete system must be tested under realistic operating conditions.
☐ Compressor operating
☐ Tyre equipment operating
☐ Inverter under load
☐ Lighting operating
☐ Battery voltage monitored
☐ Charging system checked
☐ No excessive cable/connection heating
☐ No unexpected circuit breaker/fuse operation
☐ System remains stable under expected working load
Record results:
Battery voltage before test: __________
Battery voltage during load: __________
Inverter load: __________
Charging voltage/current: __________
Test duration: __________
Notes: ____________________________________________
Stage 10 – Final Quality Control & Completion
Before the vehicle is considered finished:
☐ All fixings checked
☐ Electrical connections inspected
☐ Cables secured and protected
☐ Battery/batteries secured
☐ Terminal covers fitted
☐ Circuit protection checked
☐ Equipment mounting checked
☐ Air system checked
☐ No tools left in vehicle
☐ No loose components
☐ Vehicle cleaned
☐ Cab checked
☐ Vehicle starts correctly
☐ Dashboard warning lights checked
☐ Final photographs taken
Mandatory Completion Photographs
Take clear photographs of:
☐ Finished load area
☐ Tyre changer mounting
☐ Wheel balancer mounting
☐ Compressor installation
☐ Battery installation
☐ DC-DC charger
☐ Inverter
☐ Main circuit protection
☐ Control panel
☐ Cable installation
☐ Lighting
☐ Exterior of completed vehicle
Upload photographs to MY Workshop.
Installer Sign-Off
Installer: ______________________________
Date completed: _________________________
All stages completed: YES / NO
Outstanding issues:
Parts required:
Installer signature: __________________________
Final QC
Checked by: _____________________________
Date: __________________________________
Approved for handover: YES / NO